Suntherm Newsletter February 2018

Up-date - Common Heating System

With the last newsletter in January, Suntherm revised our time plan in order to ensure the quality of the Suntherm heating system. And Suntherm is now 100% back on track.

At the end of 2017, Suntherm made a decision to delay the original time plan. This was done in order to ensure the quality of one of the components of the system. We still find that this decision was right in order to make sure that quality and reliability will live up to our demands and specifications.

The status of the common heating system Hvidbjerg is that half of all households that have expressed their interest in participating have now received a visit by Suntherm. We are already now selecting sites for the first installations. This is due to our intension of starting the installation of these at the end of March 2018.

However, the selection of the first installation sites will not hinder other households in becoming part of the project. All remaining households will receive a visit shortly.

In the long run: The target is to install 35 Suntherm heating systems in Hvidbjerg. Currently, it is our expectation that all systems will be installed by the end of September 2018. Hence, several processes run parallel.

 

The above is a brief outline in English